Progress
| Week | Details | References & Remarks | 
|---|---|---|
| Week 1 (11 - 19 January 2010) | - Meeting with supervisor - Review on project with the other 2 teams | |
| Week 2 (20 - 26 January 2010) | - Marketing Research - Idea Brainstorming | Market Research | 
| Week 3 (27 Jan - 2 Feb 2010) | - Project Specification - Image Layering Feature | Project Specification | 
Time Schedule (Temp.)
| January | - Review on the project progress - Market Research - Application Design (e.g. Idea, Target User, theme, interface,… etc.) - Learning Objective C for further development | 
|---|---|
| Feburary | - Code implementation - Application Testing | 
| March | - Code implementation - Application Testing - Release of prototype | 
| April | - Final Application Testing including: → Unit Testing → Acceptance Testing → Stability Testing - Documentation | 
















 
  